On August 23, 2019, the Georgia State Financing and Investment Commission (GSFIC) and the Board of Regents of the University System of Georgia broke ground on a new, modern College of Mathematics and Science building at Augusta University. With a projected opening of May 2021, GSFIC approximates the cost of the facility to be $66.5 million and encompass 124,500 square feet, providing ample space for innovative laboratories that will facilitate student-centered research and increase the number of graduate programs. With the addition of these services, this facility will promote recruitment of new students and progress student achievement.

Quick Facts:

GSFIC Project Manager: Wes Berry

GSFIC Contract Compliance Specialist: Pete Carter

Design Professional: SLAM Collaborative

Construction Professional: Gilbane Construction Company

Project Timeline: 21 months

Project Cost: $66.5 million